Works Tendered and Tendered, In July, Amount To $ 1,000 Million

Works Tendered and Tendered, In July, Amount To $ 1,000 Million

Works Tendered and Tendered, In July, Amount To $ 1,000 Million

In the month of July, the Government of La Pampa, through the Ministry of Works and Public Services, goes through an agenda of important works tenders for different dependencies and localities of the Province with a total budget estimated at 1,000 million pesos. The benefited localities are Toay, Santa Rosa, General Acha, Lonquimay, Quemú Quemú, 25 de Mayo, Casa de Piedra, Alta Italia and Speluzzi.

These places in the Province are not only favored by the new buildings for social, educational and health purposes that they will have, but also during the construction process jobs are incorporated that collaborate with the economy of various sectors. In this way, the Government of La Pampa promotes and supports the works throughout the territory because they constitute genuine employment generators and reactivate local and regional economies, in addition to meeting fundamental building needs for growth and social welfare.

These include public tenders that will include the construction of five Child Development Centers (CDI) and the long-awaited Secondary School in the town of Speluzzi. The Child Development Centers, which depend on the Ministry of Social Development, are intended for the primary care of children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development, the towns of Toay, Santa Rosa, General Acha, Lonquimay, Quemú Quemú and 25 de Mayo.

The bidding order will begin with the work of the Achense Child Development Center, scheduled for July 26, 2022 at 11 a.m., with an official budget of $40,052,191, with a delivery time of 240 days. The works correspond to the construction of a building for the operation of a CDI at the intersection of Ssrmiento and Casetta streets.

It will be executed to respond to primary care for children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development. The functional complex thus developed covers a covered area of ​​220.00 square meters.

SANTA ROSA SHIFT

The public bid for the construction of the Santa Rosa Child Development Center is scheduled for July 26, 2022, at 9:00. It has an official budget of $37,741,513 and a delivery time of 240 days. The works correspond to the construction of a building for the operation of a CDI at the intersection of Río Cuarto and Sansinanea streets in the capital city.

It will be executed to respond to primary care for children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development. The functional complex thus developed covers a covered area of ​​220.00 square meters.

SPILLING

The General Directorate of Public Works contains for the opening of the national administrative act to execute the work in the northern town of Speluzzi. It will be next July 27, at 10, in the Municipal Multipurpose Room, located on Avenida 25 de Mayo s/n, with an official budget of $235,098,600 and a delivery period of 365 days.

The land is located at the intersection of Calle 4 and Calle 9, with an area of ​​4,006.02 m2. The building is proposed with a strong linear imprint with a circulation that defines the location of the spaces served (classrooms, toilets and government area on one side and special classrooms and support for the SUM on the other). On one end of the circulation an emergency exit is proposed and on the other, a contemplative patio for the library. The covered area to be built reaches 1,290.00 m2, the semi-covered area at 50%: 31.50 m2 and a total area to be built of 1,321.50 square meters. A traditional mixed construction system is proposed with an independent structure of reinforced concrete, composed of bases, columns and beams, covered with a metallic structure, aluminum carpentry and bent sheet metal with treatment, in interior doors, in all cases, the glass to be used will be safety laminated with the thickness indicated in the spreadsheets. Parasols, ceilings, subfloors, interior and exterior floors are projected.

Electrical installation and weak currents, with material approved by IRAM standards, sewage system, installation of hot and cold water, gas supply, air conditioning of the building will be carried out with central heating equipment by injection of hot air through sheet metal ducts and system fire safety.

CDI IN LONQUIMAY

For July 28, 2022, at 9:00, the public tender was scheduled to build the CDI in Lonquimay. The work has an official budget of $38,250,324 and a delivery time of 240 days. It will be located at the intersection of Italia and Avenida Roca streets in the town of Lonquimay.

It will be executed to respond to primary care for children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development. The functional complex thus developed will cover a covered area of ​​​​220.00 square meters.

CDI IN QUEMU QUEMU

On the same day, July 28, at 11:00, the Quemuense CDI will be tendered with an official budget of $41,891,002 and a delivery period of 240 days. It will be located at the intersection of Berutti and Las Heras streets. It will be executed to respond to primary care for children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development. The functional complex thus developed will cover a covered area of ​​220.00 square meters. CDI on May 25

The public tender for the construction of the Twenty-Fifth Child Development Center was scheduled for July 29, 2022, at 11:00. It has an official budget of $38,349,479 and a delivery time of 240 days. The works correspond to the construction of a building for the operation of a Child Development Center that will be located at the intersection of Chacharramendi and La Humada streets.

It will be executed to respond to primary care for children, comprehensive care for their development including nutritional assistance, early stimulation and psychomotricity, thus meeting local demand, allowing for a building that manages adequate child development. The functional complex thus developed will cover a covered area of ​​​​220.00 square meters.

LIFE RESOURCE

Another of the works is the sewerage network and treatment plant in Alta Italia, which will be carried out by the Provincial Water Administration (APA), dependent on the Ministry of Works and Public Services of the Provincial Government. Currently, the sewage effluents generated in homes, businesses and institutions, in the town of Alta Italia, are disposed of in the subsoil through individual treatment and final disposal systems. These systems can dispose of the effluent in crude form to the subsoil through an absorbent well or filter trench, or intermediate pretreatment in a septic chamber, which causes inconveniences in the community because it is an old system that is not recommended for the quality of life of the population. .

The sanitation works planned for the town are basically made up of a network of sewage collectors installed by sidewalk with their corresponding manholes, home connections, pumping stations, conduit to a treatment plant, a combined activated sludge treatment system, discharge of the effluent for the first stages of operation and provision for the exit of the treated liquids towards a surface water body (lagoon), known as “El Bajo de Sola”.

Initially, the area called “First Stage Main Basin” will be carried out, which will be executed jointly with the treatment plant.

In this first stage of the work, it is planned to enable some 16,920 meters of sewage collector network, which will link 695 household connections to the system, with 2 pumping stations, one intermediate and one main, which directs all the domestic sewage drains to the Processing facilities.

From the Main Pumping Station, the raw sewage discharge pipe will depart towards the Treatment Plant, which will be located to the southwest of the town, on the Municipal property on the Rural Road. The works have been designed to meet the needs of the projected population in 20 years.

HEATED SWIMMING POOL

In Casa de Piedra the swimming pool will be refurbished, the work deals with maintenance and conservation work on the interior conditioning system, which has faults in the swimming pool water recirculation system and difficulties in starting up the pool air conditioner.